I ordered this board several years ago and never downloaded the information for it. I don't even KNOW anymore what it is supposed to build. Could someone be so kind as to point me in the correct direction for download information. thank you!

75 Views

Correct!

Elator Power Transformer


67 Views

rectifier 1N4007

Hi andrea, first please have a look at drawing 18w Brit , rectifier. drawing says, leg 2 and 7. I believe it should be leg 1 and leg 7 ?


then the question, what is the reason to use 1n4007 and 3KV,0.001uf cap to and between the legs 2(or1) and 7 ?


Best, Henri


58 Views
Brooks Kay
Brooks Kay

SOLO100 Choke

I'm a little confused. according to the build of materials (BoM), I'm supposed to source a 10H 125mA choke for this build. According to the schematic and layout, it's calling for 10H 200mA.

I already sourced a 10H 150mA choke. Will this be sufficient, or do I need to return it for a 10H 200mA choke? Thanks for the help! as a point of reference, I am building the LDR version.

59 Views

SOLO100 choke is a forth section telescopic access pole used for reaching and testing fire alarm and smoke detectors at heights. this device are available in market easily.


Visit Here https://privatetourinla.com/ Private Tour in LA

© 2023 by AmBits. Proudly created with Wix.com

bottom of page